Older decisions and UZP explanations for procurement specifications
Seven selected judgments and five UZP materials: samples, options, quality criteria, accessibility, labels and procurement preparation.
Earlier decisions need their historical legal context. UZP explanations and guidance are not judgments or binding legislation. Our editorial suggestions are identified separately. Original document dates differ from the date added here.
Seven judgments in the case-law collection
- C-601/13 – Ambisig – Team experience as a quality criterion · 2015-03-26
- C-14/17 – VAR i ATM – When must equivalence be demonstrated? · 2018-07-12
- KIO 1240/15 – Local facilities at the bid stage · 2015-06-23
- C-131/16 – Archus and Gama – Sample clarification or a new bid? · 2017-05-11
- C-448/01 – EVN and Wienstrom – Environmental criteria must be verifiable · 2003-12-04
- KIO 636/23 and KIO 650/23 – Options and comparable pricing · 2023-03-24
- KIO 217/26 – A clarified time-based service option · 2026-02-23
Each entry includes the outcome, reading scope, official source and an editorial implication.
Go to: Preliminary market consultations — UZP guidance · Specification authors and impartiality declarations · Needs and requirements analysis — UZP recommendations · UZP examples: accessibility and social aspects · Social labels — UZP publication
Preliminary market consultations — UZP guidance
Webpage publication: 16 June 2025 · Publisher: Public Procurement Office (UZP)
Essence of the explanation: Consultations before launching a procedure are optional. They help identify market solutions, while their organisation and use must preserve competition and equal treatment.
Editorial implication: Ask about parameters, timing, costs and acceptance; document responses and justify the requirements chosen for the specification.
Official source → · PDF UZP · Checked: 9 October 2026.
Specification authors and impartiality declarations
Webpage publication: 21 April 2022 · Publisher: Public Procurement Office (UZP)
Essence of the explanation: UZP distinguishes preparing a specification alone, without influencing the outcome or other procedural actions, from answering tender-document questions or evaluating bids. The latter involvement may trigger a declaration; the person’s actual role matters.
Editorial implication: Record who drafts, answers questions and evaluates compliance; assess the declaration obligation for each role.
Official source → · Checked: 9 October 2026.
Needs and requirements analysis — UZP recommendations
Material publication date: not established · Publisher: Public Procurement Office (UZP)
Essence of the explanation: The material structures needs, own resources, delivery options, costs, lots and risks. It contains historical 2020 thresholds and conversion figures; do not copy them as current values.
Editorial implication: Use a checklist: need and result, own resources, options and costs, lots, procedure and risks. Present Article 83 also covers increasing competition. The obligation concerns public contracting authorities’ classical procurement at EU thresholds or above, subject to statutory exceptions.
Official source → · PDF UZP · Checked: 9 October 2026.
UZP examples: accessibility and social aspects
Publication year: 2024; exact date not established · Publisher: Public Procurement Office (UZP)
Essence of the explanation: UZP gives procurement-document examples covering reserved contracts, labels and accessibility, including conferences, promotional materials and coffee service. Clauses require adaptation to the particular service.
Editorial implication: Connect each requirement to evidence, the bid, contract and acceptance. Separate minimum accessibility from additional scored quality. Check present rules and guidelines; the material also contains older references.
Official source → · Checked: 9 October 2026.
Social labels — UZP publication
Publication year: 2022; exact date not established · Publisher: Public Procurement Office (UZP)
Essence of the explanation: The publication explains how labels evidence social features of products and services and describes fair-trade schemes. It is a catalogue and explanation, not a requirement to use a particular mark in every specification.
Editorial implication: Define the needed features and check what a label proves. Apply Article 104 rules on equivalent labels and other evidence. Verify the present status of each certification scheme separately.
Official source → · Checked: 9 October 2026.
Legal reference for present use
Compare the historical material with Pzp, consolidated text: Dz.U. 2026 item 793 (PDF). It reflects the legal state on 25 May 2026; check later amendments and rules applicable to the procedure. Do not reuse historical thresholds.
Prepare your specification
Use the explanations when defining requirements and checking the draft.
Start free preview